Earned Value Analysis (EVA) gives a snapshot of whether your project is on time and on budget. Three key numbers: PV (Planned Value — what work should be done by now), EV (Earned Value — what work is actually done, valued at the budget rate), and AC (Actual Cost — what you actually spent). Variances: CV = EV − AC (positive is under budget), SV = EV − PV (positive is ahead of schedule). Performance indices: CPI = EV/AC (>1 is efficient), SPI = EV/PV (>1 is ahead). The Estimate at Completion: EAC = BAC/CPI (most common). ETC = EAC − AC. TCPI = (BAC − EV)/(BAC − AC) tells you how efficiently you must work from now on.
The project is under budget (spending less than planned for the work done) and ahead of schedule (more work done than planned). Both indices above 1.0 = good news.
★★ Estimate at Completion (EAC)
A building project has a Budget at Completion (BAC) of P5,000,000. To date: EV = P1,500,000, AC = P1,800,000. Calculate the Estimate at Completion assuming the current cost efficiency continues.
TCPI = 1.077 means you need to get P1.077 worth of work done for every P1.00 spent for the remainder of the project. Since the current CPI = 3M/3.5M = 0.857, achieving TCPI = 1.077 is very unlikely — the project will likely exceed its budget.