Water Demand Forecasting
Water-supply problems often estimate future population and convert demand into discharge or required pumping capacity.
Water-supply problems often estimate future population and convert demand into discharge or required pumping capacity.
Hydrology items include water balance, areal rainfall, rainfall intensity, and runoff volume.
Storm sewer discharge is commonly estimated using the rational method. Keep units consistent with the coefficient form required by the problem.
After finding design discharge, size the sewer using Manning's equation for the selected slope and roughness.
A reservoir supplies 0.12 m3/s. If consumption is 0.60 m3/person-day, estimate the population served.
Answer: The reservoir can serve about 17,280 persons.
A municipality had a population of 45,000 in 2005 and 63,000 in 2020. Using geometric (exponential) growth, forecast the population in 2045 and determine the required average daily supply pipe capacity in L/s if the per capita consumption is 180 L/person-day. Then compute the peak daily demand if the peak factor is 1.80.
Determine the geometric growth rate $r$ from 2005 to 2020 (15 years):
Forecast for 2045 (40 years from 2005):
Answer: Forecast population 2045 ≈ 110,400. Average daily demand Q = 230 L/s. Peak daily demand = 414 L/s. Distribution mains must be sized for the peak demand, while treatment and source facilities are typically designed for average annual demand.
A storm drainage system serves a combined catchment area of 8.0 ha consisting of three sub-areas: residential rooftops (2.0 ha, C = 0.90), lawn/parks (3.5 ha, C = 0.35), and paved roads (2.5 ha, C = 0.85). The design rainfall intensity for the storm duration and return period is i = 75 mm/hr. Using the rational formula Q = CiA (with A in hectares and i in mm/hr, use appropriate conversion), find the design peak discharge in m³/s.
For a composite catchment, compute the area-weighted runoff coefficient:
Apply the rational formula $Q = CiA$. Convert: $i = 75$ mm/hr $= 75/1000/3600$ m/s $= 2.083 \times 10^{-5}$ m/s. Area $A = 8.0$ ha $= 80{,}000$ m²:
Alternatively, using the shortcut formula $Q = CiA/360$ with $i$ in mm/hr and $A$ in hectares gives $Q$ in m³/s:
Answer: Design peak discharge Q = 1.073 m³/s ≈ 1.07 m³/s. The weighted C of 0.644 reflects the dominant contribution of impervious surfaces (rooftops and roads), which produce high runoff. Green areas with C = 0.35 act as natural retention and reduce the overall coefficient slightly.
A water supply reservoir receives inflow and must meet a constant demand. Monthly inflow data (in million m³) for a dry year are: Jan=3.2, Feb=2.8, Mar=4.5, Apr=6.1, May=5.3, Jun=2.4, Jul=1.2, Aug=0.9, Sep=1.5, Oct=2.6, Nov=3.8, Dec=4.0. Total annual inflow = 38.3 million m³. If the demand is uniform at 38.3/12 = 3.192 million m³/month, determine the required storage capacity using the cumulative surplus/deficit method.
Monthly demand = 38.3/12 = 3.192 million m³/month. Compute monthly surplus (+) or deficit (−):
The required storage is the maximum cumulative deficit (total drawdown from peak to trough). Track cumulative deficit from the point where reservoir is full (after the wet season surplus):
Answer: Required reservoir storage capacity = 7.36 million m³. This is the volume that must be stored during the high-inflow months (Mar–May) to sustain the constant demand through the low-inflow dry season (Jun–Oct). The mass curve (Rippl) method identifies this as the maximum cumulative net deficit during the dry season.
A circular concrete sewer pipe (Manning's n = 0.013) must carry a peak design discharge of 0.85 m³/s flowing full. The available slope is S = 0.0006. Determine the required pipe diameter (to the nearest 50 mm standard size) and verify that the self-cleansing velocity criterion of V ≥ 0.60 m/s is met.
For a circular pipe flowing full: $A = \pi D^2/4$, $P = \pi D$, $R = D/4$.
Compute: $\ln(0.14512) = -1.929$, $0.375(-1.929) = -0.7234$, $e^{-0.7234} = 0.4851$ m.
Answer: Required diameter ≈ 485 mm; use 500 mm standard sewer pipe. Full-pipe velocity = 4.33 m/s, which far exceeds the 0.60 m/s self-cleansing minimum. In practice, designers also check that velocity does not exceed about 3 m/s for non-reinforced concrete to prevent erosion — the 4.33 m/s here suggests a lined or reinforced concrete pipe should be specified.
A 500 km² catchment receives annual average rainfall of 1800 mm. Stream gauging at the catchment outlet records an average annual runoff of 720 million m³/year. Evapotranspiration estimated from the Penman method is 850 mm/year. No significant change in surface storage is observed (ΔS = 0). Compute: (a) total annual rainfall volume, (b) the annual evapotranspiration volume, (c) the groundwater recharge (deep percolation) from the water balance equation $P = Q + ET + G + \Delta S$.
Apply water balance: $P = Q + ET + G + \Delta S$ (with $\Delta S = 0$):
A negative result means the stated values are inconsistent — outflow + ET > precipitation. This indicates either (1) groundwater is being mined (net outflow from storage), or (2) the ET estimate is too high, or (3) there is interbasin groundwater inflow. Recheck: if ET = 850 mm over the 500 km² catchment, ET volume = 425 million m³. But Q = 720 million m³ and P = 900 million m³, so $G = 900 - 720 - 425 = -245$ million m³.
Correcting the problem to ET = 550 mm (realistic for the given P and Q):
With Q = 480 million m³ instead (runoff coefficient = 480/900 = 0.533):
Answer (corrected scenario): P = 900 million m³/yr, ET = 275 million m³/yr (550 mm), Q = 480 million m³/yr. Groundwater recharge G = 145 million m³/yr (290 mm equivalent depth). The water balance equation $P = Q + ET + G$ is the fundamental tool in hydrology for partitioning precipitation into its components — errors in any one term propagate directly into the others.